“villanova” Residential Complex

Datos de Proyecto

Ubicación: Vienna-Schwechat, Austria

  • 4 apartment buildings with 5 upper floors each, which are linked by 2 basement floors
  • Mansion-like group of buildings on the plot of a former brewery with a total of 100 apartments at Alnovaplatz, close to the city center 

Requerimientos

  • Completion of the shell structure in only 12 months construction time
  • 20 cm to 30 cm thick reinforced concrete walls for the upper floors, basement walls and floor slabs

Cliente

Swietelsky Baugesellschaft m.b.H.
Hochbau Ost, Grp. Nussdorf o. d. Traisen, Austria

Beneficios para el cliente

  • MX tie technology which can be operated from one side, the reduced number of tie points and at the same time the fact that no spacer tubes and cones are necessary with MAXIMO formwork, helped to save precious construction time
  • In particular the logical, clearly indicated assembly sequence of SKYDECK and the easy handling due to the lightweight aluminum parts reduce the shuttering times
  • By using the SKYDECK drophead, the panels and main girders can be used for the next concreting section already at an early stage. This helps to reduce the necessary amount of material on site and saves costs.
Karl Derler
Supervisor

With MAXIMO and SKYDECK, we chose the right systems for this construction project. Through our collaborative efforts, we were able to maintain the tight schedule for the shell and saved on additional costs.

Solución PERI

  • MAXIMO wall formwork for basement walls and also for the 20 cm to 30 cm thick reinforced concrete walls of the upper floors
  • Systematic forming of the floor slabs with SKYDECK panel slab formwork
  • Forming of the reinforced concrete columns with SRS steel circular column formwork – partly in combination with MAXIMO elements